Sprint 4 includes the following tasks:

  1. User Documentation
  2. Implementation of Mobile Frontend
  3. Code Quality
  4. Build System, Continuous Integration, and Delivery
  5. Project Management and Project Report

Meeting 1 (November 21st, 2019)

Trottier 0th Floor Room 0070 17h00-20h00

  • Discussed and planned what to be done for this deliverable
  • Made some changes and fixed the reviews section in the frontend
  • Started planning the mobile frontend
  • Started planning the presentation

Minutes submitted by Mert Gurkan on 2019-11-21 @ 20:30

Meeting 2 (November 27th, 2019)

Trottier 0th Floor Room 0070 16h00-19h00

  • Worked on the mobile frontend
  • Worked on the presentation
  • Completed the presentation slides

Minutes submitted by Mert Gurkan on 2019-11-27 @ 19:10

Meeting 3 (November 29th, 2019)

Trottier 0th Floor Room 0070 17h30-20h00

  • Started User Documentation
  • Worked on the mobile frontend

Minutes submitted by Mert Gurkan on 2019-11-29 @ 20:15

Meeting 4 (December 2nd, 2019)

Trottier 0th Floor Room 0070 14h30-17h00

  • Completed the User Documentation for website
  • Worked on the mobile frontend

Minutes submitted by Mert Gurkan on 2019-12-02 @ 17:30

Meeting 5 (December 3rd, 2019)

Trottier 0th Floor Room 0070 15h30-18h00

  • Worked on the User Documentation for Android
  • Completed the mobile frontend
  • Completed the documentation
  • Discussed the possible future improvements for our project

Minutes submitted by Mert Gurkan on 2019-12-03 @ 18:30