- Architecture Modeling
- Implementation of Web Frontend
- Integration of Web Frontend with Backend Services
- Build System, Continuous Integration, and Delivery
- Project Management and Project Report
Trottier 0th Floor Room 0070 17h00-20h00
- Discussed and planned what to be done for this deliverable
- Assigned different roles to group members
- Fixed integration testing
- Started architecture modelling
- Started setting the tools for frontend
- Planning frontend
- Setting time and location for next meetings
Minutes submitted by Mert Gurkan on 2019-11-07 @ 20:30
Trottier 0th Floor Room 0060 17h00-20h30
- Finished setting the tools for frontend
- Worked on the architecture modelling
- Completed discussing which features to include in the frontend
- Started implementing the features for the frontend
- Setting time and location for next meetings
Minutes submitted by Mert Gurkan on 2019-11-14 @ 20:40
Trottier 0th Floor Room 0070 13h00-20h00
- Worked on the backend issues
- Mostly completed the architecture modelling
- Worked on the frontend features
- Setting time and location for next meetings
Minutes submitted by Mert Gurkan on 2019-11-15 @ 20:30
Trottier 0th Floor Room 0070 13h00-19h00
- Worked on the problems on the frontend
- Worked on the integration of the frontend with backend services
- Build project with Travis CI and deploy to Heroku
- Completed the architecture model
- Fixed the problems on backend
- Finished implementing the frontend
- Finalized documentation
- Reviewed the sprint and discussed what to improve for the following sprint
- Setting time and location for next meetings (next sprint)
Minutes submitted by Mert Gurkan on 2019-11-17 @ 19:10
Group 14 LUU Steven, ZENG Nelson, LIU Tian Ci, AMMAR Mehdi, GURKAN Mert