This project was born to simulate sprint planning and execution, and figure out if you can estimate tasks as a group.
It's also used to get to know Vaadin and Heroku.
Content:
Currently, I've gotten into a lot of discussions over the question: "In scrum should we pre-assign tasks during sprint planning?"
I'm absolutely for pre-assigning tasks, because:
- It's easier to address individual capacities (e.g. the never-before-heard "part-time")
- It's fairer ("You do this ugly bug, and I'll do that one.")
- It's more efficient (just give the task to whoever estimates the fastest time)
- It makes the planning faster (everybody has to understand only their own tasks, and team members can even prepare for that)
- Many bugs are already implicitly pre-assigned, because team members are experts in different things
- You don't double book people (e.g. by adding two tasks that can only be done by one person efficiently, when each of them alone would fill out the time of that person completely)
My team is against it, because:
- It's not fail-safe (if a member can't participate in the sprint, nobody can take on their tasks)
(I don't think there was ever a second argument.)
And just to address this:
- "Nobody can take on their tasks" - this is exactly what happens in our team. And we don't pre-assign. It's just that nobody will do implicitly assigned tasks. For good reason. If the expert can do it next sprint, why should I half-ass their tasks?
I have another suspicion why pre-assigning tasks is better, and that is our horrible estimations. It's clear that you never learn to estimate if you can't practice, so in that regard pre-assignments are already better. However, I have a hunch that even with good estimations it won't work if multiple people estimate, and only one of those does the task.
This project was born to simulate sprint planning and execution, and figure out if you can estimate tasks as a group.
This project makes some assumptions:
Sprint
- a sprint consists of
Task
s- tasks have a
Complexity
(i.e. "story points")- for this simulation, we have three complexities (if your standard task is 3sp, think of them maybe as 1sp, 3sp and 8sp)
- tasks have a
- a sprint has a length in days
- a sprint consists of
Member
- a team member has a work
Performance
- we have three standard performances, but you can always add your own (i.e. a team member that is good in some task and bad in others)
- a team member's estimation deviates from reality by an error margin in both directions, but on average the member estimate correctly
- a team member has a fixed set of hours they can work each day
- a team member has a work
(See SprintGenerator)
- The team
Member
s get together - A
Task
s is created from the never-ending task machine (see TaskCreator) - Each team member estimates how long it will take to do the task (for them) - for that they take the time it will take them to do the task, and use a Gaussian curve capped at their
estimationDeviation
to add a bit of variance - An operation is used to get the team's estimation from the member's ("average" right now)
- If there is still hours left in the
Sprint
, start again at 2.
(See SprintExecutor)
- The team
Member
s andTask
s get together - Tasks are sorted by complexity, so longer tasks are done earlier
- Each task is assigned to the team member who has the most time open to do it
- The team member does the task and tracks their time
To run a single sprint with its information printed on the console, use SimpleSprintExample. This will print something like this:
Team Members
============
Angie (SENIOR, 8h)
Bert (NORMAL, 8h)
Charles (JUNIOR, 8h)
Sprint Planning
===============
Estimated Hours: 240.6925148175762
Additional Hours: 0.6925148175762104
Sprint Retro
============
Remaining Hours: 40.19999999999999
Necessary Additional Hours: -0.0
(Note: the results shown are random, but representative examples are shown.)
Interesting! Our three full-time team members estimated they'd need 240 hours to do their sprint (what a precision!), but had 40 hours left at the end of it.
That is not at all what I was expecting.
To analyze why let's have a look at the task overview (SimpleSprintExample.java
will print this, too):
Angie | Bert | Charles | All | Assignee | Necessary Time | |
---|---|---|---|---|---|---|
LIO-31415 | 1.4 | 1.93 | 2.664 | 1.998 | Bert | 2 |
LIO-31416 | 5.6 | 7.728 | 13.459 | 8.929 | Bert | 8 |
LIO-31417 | 5.6 | 8.8 | 10.155 | 8.185 | Charles | 16 |
LIO-31418 | 11.2 | 16.819 | 35.258 | 21.092 | Angie | 11.2 |
LIO-31419 | 1.4 | 1.989 | 4.274 | 2.554 | Angie | 1.4 |
LIO-31420 | 11.2 | 14.993 | 48 | 24.731 | Bert | 16 |
LIO-31421 | 11.2 | 15.727 | 41.719 | 22.882 | Charles | 32 |
LIO-31422 | 5.6 | 7.496 | 19.198 | 10.765 | Angie | 5.6 |
LIO-31423 | 5.6 | 7.908 | 22.148 | 11.885 | Angie | 5.6 |
LIO-31424 | 5.6 | 8.534 | 17.005 | 10.38 | Bert | 8 |
LIO-31425 | 5.6 | 8.218 | 20.025 | 11.281 | Angie | 5.6 |
LIO-31426 | 5.6 | 8.428 | 11.389 | 8.472 | Bert | 8 |
LIO-31427 | 1.4 | 2.126 | 4.599 | 2.709 | Angie | 1.4 |
LIO-31428 | 5.6 | 8.22 | 23.581 | 12.467 | Charles | 16 |
LIO-31429 | 1.4 | 2.137 | 3.352 | 2.296 | Bert | 2 |
LIO-31430 | 1.4 | 1.916 | 3.716 | 2.344 | Angie | 1.4 |
LIO-31431 | 11.2 | 16.626 | 30.087 | 19.304 | Angie | 11.2 |
LIO-31432 | 1.4 | 2.129 | 3.301 | 2.277 | Bert | 2 |
LIO-31433 | 1.4 | 1.8 | 2.681 | 1.96 | Angie | 1.4 |
LIO-31434 | 1.4 | 2.024 | 2.751 | 2.058 | Angie | 1.4 |
LIO-31435 | 11.2 | 14.619 | 25.173 | 16.997 | Bert | 16 |
LIO-31436 | 1.4 | 2.031 | 3.59 | 2.341 | Bert | 2 |
LIO-31437 | 11.2 | 14.4 | 16 | 13.867 | Angie | 11.2 |
LIO-31438 | 1.4 | 1.878 | 4.334 | 2.537 | Angie | 1.4 |
LIO-31439 | 1.4 | 2.153 | 3.831 | 2.461 | Bert | 2 |
LIO-31440 | 1.4 | 2.093 | 2.663 | 2.052 | Charles | 4 |
LIO-31441 | 5.6 | 7.2 | 15.038 | 9.279 | Angie | 5.6 |
LIO-31442 | 1.4 | 2.14 | 4.222 | 2.587 | Angie | 1.4 |
Let's take a look at our team members first:
- Angie needs 70% of the time to finish tasks and is a perfect guesser
- Bert needs 100% of the time to finish tasks and guesses with 10% deviation
- Charles needs 200% of the time to finish tasks and guesses with 50% deviation
The interesting tasks are:
- LIO-31417 - the estimate is 8 hours, but Charles needs 16 hours to do it (and for this task in particular he was a horrible guesser) → 8 hours more are needed
- LIO-31418 - both Bert and Charles try to increase the estimation, but Angie only needs 11 hours → 10 hours less are needed
- LIO-31420 - Charles increases the estimate by a lot, but Bert only needs 16 hours → 8 hours less are needed
- LIO-31421 - Charles needs his time with the issue → 9 hours more are needed
- ...
In summary: every time Charles does a task, he needs a lot more time than estimated, Bert's time is a bit better than the estimate and Angie needs a lot less time than estimated. But since Angie can do a lot more tasks than Charles her faster times sum up.
Mathematically speaking, both Angie and Bert are twice as fast as Charles. From their tasks, the additional hours of half of them are needed to allow Charles to work at his slower speed. So the additional hours of the other half is what makes up the "remaining hours".
With that knowledge we can construct another example where the team won't have this many hours remaining at the end of the sprint - we'll give Angie a second project to work on and Bert a child that makes him want to work part-time:
Member angie = Member.createSenior().workHoursPerDay(4);
Member bert = Member.createNormal().workHoursPerDay(4);
Member charles = Member.createJunior();
Result:
Sprint Planning
===============
Estimated Hours: 164.19162271153965
Additional Hours: 4.191622711539651
Sprint Retro
============
Remaining Hours: 0.800000000000002
Necessary Additional Hours: -0.0
Now sprints will finish in the time the three of them estimated, because the two faster team members will do about the same number of tasks than the slower one. (With a bit of variance - sometimes they will have 10 hours remaining, but other times they will need additionally 10 hours.)
So if each member gets the same weight in the estimations, but does not work the same number of tasks, estimating together can not work. The team tends to be faster than the estimation.
This is surprising, because ever since I joined a team that estimates together, we did not finish one single sprint on time.
So why does that not work for us?
Because Charles is not the perfect guesser this simulation made him. In fact, after estimating a couple of sprints with Angie and Bert he is very good in guessing the same numbers as them - even if he takes a lot more time. Since you do not compare estimations at the end of the sprint (and there is no way you could do that realistically), his behavior has no consequences.
Charles acts like this:
Member charles = Member.createJunior().workPerformance(task -> {
// we are in sprint planning, so just guess what Angie and Bert guess
if (task.getUserData(SprintGenerator.TASK_DATA_COLLECTED_ESTIMATION) == null) return 1;
// now I'm actually working on it, but I'm slooow
return 2.0;
});
Now the team members guess about the same value, but Charles still takes double the time. Every hour he works costs the team 30min they never estimated. Since he works 80h in a sprint, the team needs about 40h after each sprint to clean up Charles's mess.
Sprint Planning
===============
Estimated Hours: 251.91424667361778
Additional Hours: 11.914246673617782
Sprint Retro
============
Remaining Hours: 0.0
Necessary Additional Hours: 47.20000000000001
Really, team? It's not a good idea to plan a sprint with 12 more hours than possible with somebody like Charles. But the simulation proofs the theory.
How do you know this is what is happening?
This is a conversation I actually had when I estimated my needed time:
- Team: "Why would you estimate so much more than us?"
- I: "Because I've never heard of the technology before and I'll need some time to learn it."
- Team: "But it's easy!"
- I: "So... you want me to use your estimation?"
- Team: "Yes."
This might be because this particular team doesn't know much about scrum, but I've seen it time and time again: junior members (and others with little knowledge of a task at hand) will usually not estimate their needed time, but try to stay close to their peers. This is often enforced by the team, which mistakenly asks the same questions as for their story point estimation (where it is absolutely okay and even preferred to have everybody guess the same value).
How do we fix this?
I have honestly no practical idea besides pre-assigning tasks.
A straight-forward way would be to forbid questions towards the time estimations, even if the estimation is off by a lot. But this would work against the case were one or many team members did not understand the task correctly and questions should have been asked.
Since the entire estimation only works if each team member estimates well, this should be trained. For this you would need to make team members find their original estimation and see how much off they were eventually. For this purpose they should ignore the team estimate. Which of course makes monitoring the tasks hard.
But honestly: I estimated I need 10 hours for a task, 4 team members estimated 30min each - which is an average of 2h 30min. Why do I have to beg for the remaining 7h if I never agreed to do it in that time? But that is what is happening again and again. And the team members wouldn't be able to do this in 30min either - they just don't care because they know they won't be doing that task. (Yes, this is an actual example that happened like this multiple times.)
Which is, in short, the entire reason why team estimations do not work.
There is one solution that works, but it is not really practical: use teams were everybody has a similar performance. That way junior estimations that just stay close to the group won't cost the team too much time.
This is just a simulation, and humans don't act like computer programs. So in reality, these problems (additionally) arise:
- of course, most glaringly, you can't calculate hours from story points (but somehow we have to create different-length tasks)
- most of them time, team members will not estimate correctly on average; from what I've seen, even skilled team members will (almost) always over-estimate or under-estimate, even if only by a little
- the performance of a team member is not fixed - their health, the day of the week, the hour of the day, distractions, etc. change their needed time
- another thing that changes the "needed time" is the "estimated time" - if a team member is a lot faster than estimated, they might use the remaining time to do something else that is related; if they are a lot slower they might be able to rush things or "outsource" parts of the task into other tasks
With this project we can test objective factors that change how the sprint gets executed.
Clearly these factors are important:
- estimation performance of team members (
Member#estimationDeviation
) - the time team members can invest in the sprint (
Member#workHoursPerDay
)
But there are other factors.
Let's assume we have two team members (Angie and Bert) who are able to work 40h each for the sprint. We have 41 tasks: 1 task estimated at 40h and 40 tasks estimated at 1h.
Option 1: Angie takes on the 40 small tasks, and Bert takes on the 1 big task, so both will be finished in time.
Option 2: Angie and Bert both do 20 of the small tasks each for half of the sprint, and then either of them has to the big task. The sprint gets overbooked by 20h (and one team member is idle for 20h).
Mathematically speaking, these options might be identical (Angie has to use 20h of the next sprint, while Bert is able to finish tasks worth 20h from the next sprint) - for real humans they're not.
If Angie is doing the big task, she will be disheartened by not being able to finish it on time (yes, even if she should not have been able to) and the meetings at the end of the current sprint and start of the new one will disrupt her work even more.
Bert's performance will slow down once he realizes he will be idle for the second half of the sprint.
The entire team's moral will suffer due to lot of sprint changes (adding 20h of tasks for Bert for a 80h sprint is a lot).
So in conclusion the team is better off doing big tasks earlier.
This simulation does not have a priority for tasks, but it's clear why priority changes the sprint performance: in the above example, what is one possible reason Angie and Bert did the small tasks first? Priority.
So the bottom line is: since the team and the product owner are already on the same page that the current sprint contains the most important tasks to do right now, the team should be able to do them in any order they wish, so that they might be able to finish the sprint on time.
Will this work? Probably not.
Most people have a tendency to do small tasks first anyway, because it helps build motivation for bigger tasks. And if there is a chance you won't even need to do the big task, then some might close their eyes and lalala their way through the small tasks.
Human psyche is interesting and does not seem to work well with unassigned tasks. It's the bystander effect of software development.
From a purely mathematical standpoint, it is not possible to estimate as a team if the actual work performance varies a lot, the team members shame each other from voting a needed higher time and if nobody checks the individual estimations (instead of the team estimation) versus actual needed time.
From the standpoint of someone with management experience, I don't see not pre-assigning tasks working either. The more junior the team, the less this is working. Because junior humans do usually not have the best skills in managing themselves - much less overlooking an entire sprint worth of tasks to figure out what to do in which order.
Additionally, pre-assigning tasks adds an important motivator to the mix: even if the team fails to do sprints on time, I'm able to judge if I did my tasks on time. Every sprint I can improve my estimations and my performance until I am content with my performance - completely independent from what the team is doing. All the while managers can help team members that struggle to finish their sprints on time.
So in conclusion: pre-assign tasks. It's as easy as that. Give your team members the option to learn to estimate tasks and manage their own workload. Let them earn the praise for finishing their part of the sprint or improving themselves compared to the last sprint. Have shorter meetings where team members won't have to concentrate for hours on end. And most importantly: finally finish sprints on time.
I tried some stuff out in this project. For myself (and whoever might care), here are some notes that might help me later:
- to see how this project is used, see the examples
- to run the Vaadin project, run
mvn jetty:run
and open http://localhost:8080 in browser - to see what still needs to be done see the open issues, the executed tests, and the code coverage
- to update the test documentation run
mvn verify -Pdoc
This project is connected to