Skip to content

Milestones

List view

  • Due by January 15, 2014
    15/15 issues closed
  • A version in between versions early and late. For things that were late or are under testing for the late version.

    Due by July 31, 2013
    24/24 issues closed
  • Version 2.0: M24 deliverable: "Cassandra Final Platform".

    Due by October 31, 2013
    60/60 issues closed
  • Version 1.0: M18 deliverable: "Cassandra Early Platform".

    Due by April 30, 2013
    47/47 issues closed
  • Version released prior to the project review.

    Due by January 8, 2013
    10/10 issues closed
  • The version enables you to create a simulation and run it.

    Due by November 30, 2012
    42/42 issues closed
  • Provides basic functionality with respect to: a) the GUI/Client, b) the Platform/Server and c) the Simulation module.

    Due by September 16, 2012
    9/9 issues closed