Generation and ObservedGeneration

Problem

A client should be able to decide if the reconciliation of the latest Spec update has been finished by looking at the Status field of the CR. The Status.Conditions, and especially the Ready condition in that list, can be used to determine the result of the last reconciliation run. However the conditions alone cannot tell which version of the Spec was used for the last reconciliation, they cannot indicate if there is a newer Spec update that has not seen by the controller and therefore hasn't reconciled yet.

Solution

K8s maintains a Generation field for each CR. When the Spec field of the CR is updated the Generation of the CR is automatically incremented.

To allow the client to decide if the Status field talks about the latest version of the Spec the Status field should tell which version, generation, the Status is referring to. This is implemented by the Status.ObservedGeneration field. This field contains the Generation value of the Spec the controller last saw and therefore the Spec version the Status is referring to.

Usage

If a client updates the Spec field of a CR and wants to decide when such Spec changes are applied to the running system, then the client needs to look at two fields in the CR Status:

  • If the Status.ObservedGeneration == Generation then the client can be sure that the controller seen the last Spec version
  • If the Ready condition's State is True in the Status.Conditions list then the client can be sure that the last reconciliation finished successfully.
if subCR.Generation == subCR.Status.ObservedGeneration &&
	subCR.Status.Conditions.IsTrue(condition.ReadyCondition) {
        // subCR is successfully reconciled the latest Spec update
}

If the Generation > Status.ObservedGeneration then the subCR controller haven't seen the new subCR.Spec so the client needs to wait.

However Generation < Status.ObservedGeneration case is also a possibility even if it is a strange one. At a first look one can say that this means the Spec's generation went backwards and that should not happen. However it can happen in a valid case too. Consider the following sequence that leads to this situation:

  1. our client updates the subCR and reads back that its Generation is now N
  2. another client updates the subCR so its Generation is now N+1
  3. the subCR controller reconciles the latest spec and sets ObservedGeneration to N+1
  4. our client reads the subCR.Status and sees ObservedGeneration N+1 while it sees Generation as N. Note that Status is a subresource in the API so it can be read independently. In this case our client cannot decide if the subCR.Spec is according to its needs, maybe the other client set something on the Spec that our controller needs to reset. So in this case our client should not state that the subCR is up to date but instead re-read the spec (if the client is in a reconciler the requeue the reconcile) and update the subCR.Spec again if needed.

Implementation

The Generation field is implemented automatically.

The Status.ObservedGeneration needs to be implemented by every controller individually. This field needs to be bumped to the value of the Generation field at the start of each Reconcile run, after the Status.Conditions field is reset to signal that a new Spec version is being reconciled and therefore the old condition values are not valid any more.

When a CR depends on one or more sub CRs

We have multiple cases when the Readiness of a parent CR depends on the status of other sub CRs (e.g. Glance CR Status depends on one or more GlanceAPI CRs Status). If the above implementation is in place then the ObservedGeneration of the parent CR will not depend on the ObservedGeneration of the sub CRs. But the Readiness (the Ready=true state) of the parent CR depends on the subCR.Status fields (mostly the Status.Conditions) and therefore it needs to consider what Spec Generation those Status fields are referring to. So the subCR.Status.ObservedGeneration needs to be included in the parent CR's Readiness calculation. This is needed as the subCR's Ready condition alone cannot tell if the controller of the subCR see the latest Spec update from the controller of the parent CR.

When a CR depends on Pods

We have CRs that are managing Pods via Deployment, StatefulSet or other similar deployment resources. These deployment resources have ObservedGeneration as well. The ObservedGeneration of the CR should not depend on the ObservedGeneration of the deployment resource. But the Readiness of the CR needs to consider Status fields of the deployment resource like ReadyCount. However that ReadyCount might refer to an older Spec generation therefore the CR needs to also check the ObservedGeneration of the deployment resource when using the ReadyCount (or other Status fields) to calculate it's Readiness.