PlanScript — Design

Purpose

Plaintext-first project scheduling, inspired by Beancount and hledger.

The .plan file is the authoritative project definition. The system parses it into a project model, validates it, derives a CPM schedule, tracking state, costs, and reports, and exposes the results through a CLI. GUI and plugin interfaces remain future work.

The central design rule:

Derived information must not become a second source of truth.

Plan definition and tracking history are authoritative and live in the file. Schedules, resolved budgets, variances, forecasts, and reports are derived and never written back as authoritative data. (Serialization exists but is not yet wired into the CLI; see planscript/serializer/.)

Design Principles

  1. Plaintext readability over structured-data convenience. Do not drift toward JSON/YAML.
  2. Avoid quoting and unnecessary punctuation; punctuation must communicate meaning.
  3. Keep task lines short. Dependencies, budgets, and metadata get their own indented lines.
  4. Descriptive metadata is separate from scheduler input.
  5. Hierarchy in a task number is organizational; it never implies a dependency.
  6. CPM stays pure: the scheduler operates on duration/offset values and dependency relationships.
  7. Dates are mapped to and from schedule offsets in a calendar layer.
  8. Do not call something a constraint if it does not change the schedule.
  9. Prefer a small number of powerful concepts (a zero-duration task is a milestone; there is no milestone class).
  10. Resolve the semantic model before inventing syntax.
  11. Invalid input fails explicitly with a line number; nothing is silently repaired.

Architecture

                        .plan FILE (authoritative)
                              │
                     ┌────────┴────────┐
                     │                 │
              plan definition     tracking history
                     │                 │
                     ▼                 ▼
                  Parser           (events)
                     │                 │
                     ▼                 │
              Project model ◄──────────┘
                     │
        ┌────────────┼────────────┬───────────┬──────────┐
        ▼            ▼            ▼           ▼          ▼
   Scheduler      Tracker      Analyzer    Budgeter   (Serializer)
        │            │            │           │          │
        ▼            ▼            ▼           ▼          ▼
    Schedule     actuals /     variance    Budget     .plan text
                 status       reports    (derived)
        └────────────┴────────────┴───────────┘
                     │
                     ▼
              CLI: display / gantt / reporter

Package Layout

Module Responsibility
pyproject.toml Packaging metadata, Python version, and the planscript console script entry point.
planscript/__main__.py Module entry point for python -m planscript (no install required).
planscript/app.py Argument parsing, subcommands, exit codes, error reporting.
planscript/exceptions.py ParseError, ValidationError, SchedulingError, BudgetingError.
planscript/engine/parser.py Line-oriented parser: .plan text → Project.
planscript/model/project.py Project aggregate root and project-level validation.
planscript/model/task.py Task (number, name, duration, budget, metadata).
planscript/model/dependency.py Dependency, DependencyType, DependencyGraph.
planscript/model/constraint.py Constraint, ConstraintType: task-level schedule constraints.
planscript/model/hierarchy.py TaskHierarchy derived from task numbers.
planscript/model/calendar.py Calendar (working days, holidays). Model only; not yet applied.
planscript/model/budget.py Budget (resolved/derived budget).
planscript/model/schedule.py Schedule (derived CPM results and dates).
planscript/model/tracker.py Tracker, TaskEvent, TaskState, Invoice, directives and statuses: the authoritative tracking history embedded in the Project aggregate. Per-task indexes over events and invoice allocations keep derived actuals proportional to a task's own history. Lives in the model layer (it depends on no engine module), so model never imports engine.
planscript/engine/scheduler.py Scheduler: CPM forward/backward pass, float, critical paths, dates.
planscript/engine/analyzer.py Analyzer, TaskVariance: planned vs. actual variance and progress.
planscript/engine/budgeter.py Budgeter: resolves explicit and weighted budgets.
planscript/engine/forecaster.py Forecaster: forecast schedule from actuals; finished work pinned to its actual finish, remaining work floored at the data date.
planscript/engine/reporter.py ReportBuilder and report dataclasses for status reporting.
planscript/cli/display.py Table rendering, schedule/budget views, legacy interactive menus.
planscript/cli/gantt.py Textual Gantt rendering.
planscript/serializer/plan_serializer.py Project → .plan text. Incomplete; not wired into the CLI.
planscript/tests/ unittest suite (311 tests) plus shared project fixtures.
_archive/ Superseded interactive CLI and the original standalone invoice model.

Model

All model types are dataclasses. Identity is by task number; Task objects are shared by reference between the project and its dependencies, so renaming a task number keeps its dependencies attached.

Project (aggregate root)

Attribute Type Notes
name str Project name from the project: line.
start_date date | None Planned/target start. Soft; not a constraint.
finish_date date | None Planned/target finish. Soft; not a constraint.
calendar str | None Calendar name from the calendar: attribute; stored, not interpreted.
tasks dict[str, Task] Keyed by task number, kept sorted by number.
dependencies list[Dependency] All dependency relationships.
constraints list[Constraint] Task-level schedule constraints; dates are mapped to CPM offsets at schedule time.
calendars dict[str, Calendar] Declared calendars. Currently always empty.
budget Budget Derived; populated by Budgeter.
schedule Schedule | None Derived; populated by Scheduler.
tracker Tracker Authoritative tracking history and derived state.
metadata dict Project-level descriptive metadata.

Operations: add_task, remove_task (also removes its dependencies and constraints), renumber_task, sort_tasks, list_tasks, add_dependency, remove_dependency, add_constraint, get_predecessors, get_successors, get_incoming_dependencies, get_outgoing_dependencies, validate.

Project.validate() is the single entry point for model validation and runs date, summary, dependency, constraint, budget, duration, and tracking checks.

Task

Attribute Type Notes
number str Hierarchical identifier such as 4.2.a; the dictionary key.
name str Display name only.
duration timedelta | None None = summary task; 0 = milestone.
budget Decimal | None Explicit budget.
budget_wt Decimal | None Percentage weight of the budgeted ancestor.
metadata dict Free-form task metadata.

Also Task.is_milestone. A task-level calendar field is planned but not yet implemented.

Dependency and dependency types

Attribute Type Notes
predecessor Task Task that establishes the constraint.
successor Task Task whose schedule is constrained.
dep_type DependencyType FS (default), SS, FF, SF.
lag timedelta Signed offset; defaults to zero.
lag_unit str Unit the lag was authored in (h/d/w).

DependencyGraph is a derived index of the project's Dependency objects (predecessors/successors keyed by task ID). topological_sort() returns task IDs in dependency order and raises ValueError if the graph contains a cycle.

Constraint and constraint types

Attribute Type Notes
task Task Task the constraint applies to. Leaf tasks only; summary tasks are rejected.
con_type ConstraintType Soft: SNET, SNLT, FNET, FNLT. Mandatory (hard): MSON, MFON.
con_date date Authoritative calendar anchor, stored as authored.

Constraints require a project start_date to anchor them to. The scheduler maps con_date to an offset from start_date before the passes, so no offset is stored and reassigning start_date cannot leave stale derived data behind. Start-side dates map directly (con_date − start_date); finish-side dates map one day later for leaf tasks, because a leaf task's calendar finish falls the day before its early-finish offset — a milestone finishes on its start day, so no adjustment applies to it. Only leaf tasks (including milestones) may carry a constraint — a summary task's dates are derived from its children, so a constraint there would never change the schedule.

Soft constraints resolve to the more restrictive of the network and the constraint. Mandatory constraints pin the date exactly — in both the early and the late dates, so a mandatory task always carries zero total float — and raise SchedulingError when the network cannot accommodate the pin or when two mandatory constraints on one task demand different pins. The Forecaster pins completed tasks to their actual finish with a mandatory constraint, and floors every unfinished task - started or not - at the data date with a start-no-earlier-than constraint, so remaining work is projected forward from the data date rather than replayed from the actual start.

TaskHierarchy

Derived purely from task numbers: 1.2.3 belongs to 1.2 when that task exists. When an implied parent does not exist, the task attaches to its nearest existing ancestor — with 1 present but 1.2 absent, 1.2.3 is a child of 1 — so projects need not declare every level; a task with no existing ancestor is a root. This is separate from the dependency graph. API: get_parent, get_children, get_roots, get_leaves, get_leaf_ids, has_children, is_summary, get_descendants, get_ancestors, get_tree.

Calendar

id, name, working_days (0 = Monday), and holidays, with is_working_day, next_working_day, previous_working_day, add_working_days, and working_days_between.

Status: implemented as a model but not yet used by the scheduler, tracker, or analyzer. Dates are currently scheduled on plain calendar days.

Schedule (derived)

hierarchy, ordered_task_ids, early_start, early_finish, late_start, late_finish, total_float, critical_tasks, critical_paths, duration, start_dates, finish_dates.

CPM values are stored as timedelta offsets from the project's planned start day; start_dates/finish_dates are the calendar-day projections of those offsets when the project has a start_date, and None when it does not (a calculated-only schedule). Summary tasks have None float because they do not participate in CPM.

Tracker, events, and invoices

  • TaskEvent(date, task_id, directive, info) — one dated event.
  • EventDirective — START, PROGRESS, COMPLETE, NOTE.
  • TaskStatus — NOT_STARTED, STARTED, IN_PROGRESS, COMPLETED.
  • TaskState(task_id) with status and percent_complete, derived by replaying the task's events in date order (_derive).
  • Invoice(invoice_date, invoice_amount, allocations) with add_allocation and validate (allocations must equal the invoice amount).
  • Tracker(hierarchy, task_events, invoice_events) derives actual_start, actual_finish, actual_dates, actual_duration, actual_cost, and get_task_state.

Actual dates for summary tasks are rolled up from descendants: earliest actual start, latest actual finish (and a summary is only finished when all children are).

Analyzer (derived)

Analyzer(project, as_of) computes start_variance, finish_variance, duration_variance, task_variance, cost_variance (actual cost minus resolved budget for one task), total_cost_variance (project actual minus budget total), project_actual_start, and project_progress (duration-weighted percent complete across leaf tasks). Schedule variance is positive when later than planned; cost variance is positive when over budget.

Engines

Scheduler — CPM

Scheduler().calculate(project) -> Schedule runs these stages:

  1. Build a TaskHierarchy and a DependencyGraph.
  2. Topologically sort tasks by dependency (cycle ⇒ ValidationError at validation time).
  3. Forward pass — for each leaf task, earliest start is the maximum imposed start across its predecessors:
    • FS: ES(succ) = EF(pred) + lag
    • SS: ES(succ) = ES(pred) + lag
    • FF: EF(succ) = EF(pred) + lag, then ES = EF − duration
    • SF: EF(succ) = ES(pred) + lag, then ES = EF − duration Tasks with no predecessors start at offset 0. EF = ES + duration. Soft constraints then raise the candidate: SNET with the constraint offset, FNET with the offset less the duration. Mandatory constraints are applied last: MSON/MFON pin the candidate exactly and raise SchedulingError when the network pushes past the pin, so the outcome does not depend on the order constraints were added.
  4. Backward pass — project duration is the maximum early finish; latest finish starts there and propagates back through successors. Soft constraints then pull the candidates in: SNLT on the late start, FNLT on the late finish. Mandatory constraints then pin the late dates to the same pins (or raise), which is what leaves a mandatory task with zero float. In both passes the more restrictive of the network and the constraint wins.
  5. Float — total_float = LS − ES. Summary tasks get None.
  6. Critical tasks — total float zero or negative. Negative float means a soft constraint cannot be met without violating the network; those tasks are over-constrained and stay critical so they remain visible.
  7. Critical paths — walks the sub-graph of critical tasks connected by tight dependencies (those that actually impose the successor's early start). Branches produce multiple paths.
  8. Dates — offsets are projected onto calendar days from the project's start_date. A milestone finishes on its start day; other tasks finish one day before EF. Summary dates roll up: earliest descendant start, latest descendant finish.

Rules and current limits:

  • Durations and offsets are treated as plain calendar days. The project's calendar: is not consulted yet.
  • Without a project start_date the schedule is calculated-only: start_dates/finish_dates are None. The scheduled view and Gantt chart print a note, Analyzer variance and ReportBuilder raise SchedulingError, and the status command exits 1.
  • Summary tasks are excluded from CPM and only receive rolled-up dates.
  • Constraint dates are converted to offsets from start_date before the passes (the calendar boundary), so a project with constraints but no start_date raises SchedulingError.
  • Soft constraints take the more restrictive value; mandatory constraints pin both the early and the late dates, so a mandatory task always carries zero float, and raise SchedulingError when the network cannot accommodate the pin.

Tracker — actuals

Records events and derives per-task actuals. Every derived value is measured to a single data date (as_of), which is the report's reference date and defaults to today. Events and invoices dated after the data date are ignored, so historical state is deterministic and a future-dated entry never makes a task look started or finished. future_dated_events(as_of) returns the entries a data date excluded, so callers can report them instead of silently dropping them.

  • actual_start — the task's start event; for a summary, the earliest descendant actual start.
  • actual_finish — the task's complete event; for a summary, the latest descendant finish, and only when every descendant is finished.
  • actual_duration — inclusive calendar days: finish − start + 1, or as_of − start + 1 while the task is open. Because the data date limits the events considered, an elapsed duration is never negative, and a task whose start is recorded after the data date has no actual duration yet.
  • actual_cost — sum of invoice allocations to the task up to the data date, plus all descendant costs for a summary.
  • get_task_state — replays events up to the data date to derive TaskStatus and percent_complete, raising ValidationError/ParseError for invalid sequences instead of repairing them.

Analyzer — variance

Compares Schedule and task durations against Tracker actuals at the same data date (Analyzer(project, as_of), defaulting to today):

  • start_variance / finish_variance — actual minus planned date, None until the corresponding actual exists; raises SchedulingError when the schedule has no calendar dates (no project start_date).
  • duration_variance — actual (or elapsed, measured to as_of) duration minus planned duration. Summary planned duration comes from scheduled dates (raising SchedulingError when the schedule has none). A milestone that has happened has zero duration variance; one that has not reports None.
  • planned_progress / actual_progress — 0..1 fractions for a task. Planned progress counts calendar days to as_of, inclusive of the planned start day and capped at the planned duration; a milestone counts as planned once its date is reached. Actual progress comes from the tracking events up to as_of; a milestone reports as complete or not complete, since it has no duration to measure.
  • planned_project_progress / actual_project_progress — duration-weighted averages over leaf tasks with a positive duration, so milestones and summary tasks do not weight the project figure.
  • project_actual_start — earliest actual start across tasks.
  • cost_variance / total_cost_variance — actual minus budget, where a positive value is over budget.
  • project_consumed_cost — actual cost divided by the planned budget, or None when the project has no planned budget.

Budgeter — budget resolution

Budgeter().calculate(project) -> Budget performs two passes:

  1. Allocate top-down. Each task keeps its explicit amount (which becomes the base for its own children). Weighted siblings split their nearest budgeted ancestor's amount by percentage. Shares are allocated in whole cents, with leftover cents awarded to the largest fractional shares (ties broken by task number), so weighted children always sum exactly to the parent.
  2. Roll up bottom-up. A summary task without its own budget takes the sum of its resolvable children (partially resolvable summaries sum what is known). Leaf tasks with no determinable budget are reported in Budget.unallocated rather than guessed.

Budget.total sums only root tasks, so summaries are not double counted.

Legality of an authored budget (explicit vs. weighted, sibling consistency, weight totals) is enforced by Project.validate(), not by the Budgeter.

ReportBuilder — status reporting

ReportBuilder(project, as_of, look_ahead).build() -> ProjectReport composes the analyzer and tracker into a status report:

  • Project status: Not Started (no leaf has begun), Started (work has begun but nothing is finished or progressing), In Progress, Completed (every leaf is complete).
  • Per-task ScheduleCondition: Blocked (planned start passed, a predecessor is incomplete), Late (planned start passed, predecessors complete, not started), Overdue (started but planned finish passed), otherwise On Schedule. Unstarted conditions are evaluated before overdue so un-actioned work surfaces first, and completion is judged at the data date.
  • For blocked tasks, blocked_by lists incomplete predecessors and root_causes walks the dependency chain to the terminal blockers that must actually be actioned. (Both are computed but not yet rendered: see ROADMAP.md P1-3.)
  • ProjectBudgetReport and TaskBudgetReport carry only the planned and actual amounts; remaining (budget − actual) and cost_variance (actual − budget) are derived from them, so the two can never disagree.
  • Forecast figures (Forecast Finish, Schedule Variance, and each task's forecast start, finish, and duration) come from Forecaster at the same data date: finished work is pinned to its actual finish, each unfinished task's remaining duration is floored at the data date, the forecast network runs through the normal CPM pass, and the project's schedule variance measures the forecast finish against the project's target finish (n/a when the project sets no target).
  • A value that cannot be derived at the data date is reported as n/a, never as a zero: a zero row means a real zero. A Data Notices section lists tracking entries dated after the report date, so a truncated figure is explained rather than silently dropped.
  • Milestones report no duration (no duration variance, no inclusive one-day span), and per-task budget_consumed is n/a for a task with no budget.

Example (python -m planscript status Simple.plan -ao 2026-10-05):

Status Report as-of 2026-10-05
=======================================
Project Name: Variance Test Project
    Status: In Progress

--------------------------------------
Project Schedule Report
--------------------------------------
    Planned Start: 2026-08-01
    Planned Finish: 2026-11-30
    Planned Duration: 68d
    Actual Start: 2026-08-01
    Forecast Finish: 2026-10-30
    Schedule Variance: -31d

--------------------------------------
Project Budget Report
--------------------------------------
    Planned Budget: $304,650.50
    Actual Cost: $55,862.24
    Remaining Budget: $248,788.26
    Cost Variance (actual - budget): ($248,788.26)

--------------------------------------
Project Progress Report
--------------------------------------
    Planned Progress: 100.0%
    Actual Progress: 74.1%
    Budget Consumed: 18.3%

1.1 - Kickoff
--------------------------------------
Schedule Report    Status: On Schedule
--------------------------------------
    Planned Milestone Date: 2026-08-01
    Actual Milestone Date: 2026-08-01
    Schedule Variance: 0d

--------------------------------------
Budget Report
--------------------------------------
    Planned Budget: $3,400.00
    Actual Cost: $2,500.00
    Remaining Budget: $900.00

--------------------------------------
Progress Report
--------------------------------------
    Planned Progress: 100.0%
    Actual Progress: 100.0%
    Budget Consumed: 73.5%

Forecast fields are derived by Forecaster at the report's data date: each unfinished task's remaining duration is scheduled through the normal CPM pass with a floor at the data date, while finished work is pinned to its actual finish, so Forecast Finish is the forecast network's latest date (never earlier than the data date while work remains) and Schedule Variance measures it against the project's target finish. A project with no target finish reports n/a variance rather than inventing a comparison date.

python -m planscript status Simple.plan -ao 2026-09-26 (the real data date at the time of writing) additionally prints a Data Notices section, because Simple.plan records a 3.4 start entry dated 2026-09-27 - after the report date. That entry is excluded from every figure and announced instead.

CLI

Entry points: planscript <command> <file.plan> (installed via pip install -e ., from the pyproject.toml console script) and python -m planscript <command> <file.plan> (no install required). Both run planscript/app.py:main and share the same exit codes.

Command Options Behavior
check — Parses and validates; prints the project name and Valid.
summary — Project header (name, duration when scheduled, target dates) plus task, dependency, and tracking counts. Does not schedule.
schedule -d/--dates, -c/--calculated, -g/--gantt Calculates the schedule. With no flags all three views plus critical paths are shown. Without a project start_date, the dates view and Gantt chart print a note instead of calendar output.
status -ao/--as-of YYYY-MM-DD (default today), -la/--look-ahead DAYS (default 21) Builds and renders a status report. Requires a project start_date; without one it fails with SchedulingError (exit 1).
budget -ao/--as-of YYYY-MM-DD (default today) Resolves the budget and prints the budget table.

Exit codes: 0 success, 1 expected failure (missing file, decode error, ParseError, ValidationError, SchedulingError, BudgetingError), 2 argparse usage errors. Expected failures print a one-line message to stderr; unexpected exceptions are deliberately not caught and surface as tracebacks.

Views:

  • display.view_project_summary / view_project_header.
  • display.view_schedule_calculated — ID, task, duration, ES, EF, LS, LF, float.
  • display.view_schedule_scheduled — start/finish dates and float; prints a note when the schedule is calculated-only (no start_date).
  • display.view_budget — resolved amount and basis (explicit, weight, rollup, unallocated).
  • display.view_critical_paths.
  • cli/gantt.render_gantt — textual bar chart scaled by project duration; prints a note when the project has no start_date.
  • display also still contains the earlier interactive menu functions. They are only referenced by _archive/app.py and are not part of the current CLI.

Known CLI defects (tracked in ROADMAP.md):

  • schedule prints an arrow character (→) that raises UnicodeEncodeError when stdout is redirected or piped on a Windows ANSI code page.

Serializer

PlanSerializer.serialize(project) writes a .plan document. It is a skeleton: project metadata, calendars, budgets, invoice/tracking events, and metadata are not yet emitted, lag formatting is approximate, and it writes dependency <predecessor> > <successor> … lines rather than the depends syntax the parser accepts. It is not referenced by the CLI, so the CLI is currently read-only.

Tracking design

Tracking history lives in the same authoritative .plan file as the plan (see Purpose). Event syntax, directives, and lifecycle rules are enforced by the parser and TaskState._derive and are documented in SYNTAX.md; this section records the design decisions behind them.

  • Tracking is optional. A project with no events is untracked; one with at least one valid event is tracked. A tracked project does not need every task covered: a task with no history derives as Not Started at 0%, and there is no project-level "tracking enabled" flag.
  • State is derived, never stored. TaskState replays a task's events in date order; events carry dates, not timestamps (day-level precision), and no historical snapshots are kept. The same history always derives the same state — "today" only enters when a report or analysis is given an as_of date.
  • Plan, actual, and forecast stay distinct. The plan is what was intended; actuals derive only from tracking, so a planned date passing never creates an actual start or finish; forecasts combine plan and actuals and are derived information that is never written back.
  • Explicit versus calculated progress stays a real distinction: progress means the user reported it, and complete implies 100%. Any future calculated-progress mechanism must never be presented as though the user reported it (ROADMAP.md P3-10).
  • Designed but not yet enforced — tracking on summary tasks — is listed under Current Gaps and tracked as ROADMAP.md P1-2.

Validation

Validation is layered so that each failure is reported by the layer that owns the rule:

  1. Parser (ParseError) — line-level syntax and structure: missing or duplicate project:, content before the project, unindented attributes, duplicate attributes, invalid dates, invalid durations, invalid constraint types, malformed budget lines, empty tracking date groups, unknown task references in depends/tracking/allocation lines, self-dependencies, duplicate dependencies, malformed directive arguments, and unrecognized lines.
  2. Model (ValidationError, via Project.validate()) — project start after finish, summary tasks with durations, leaf tasks without durations, dependencies touching summary tasks, cycles, negative durations, constraints on summary tasks or unknown tasks, budget legality (explicit vs. weighted, sibling consistency, weight totals, percentage bounds, budgeted ancestor required), and tracking references and invoice allocation totals.
  3. State derivation (ValidationError / ParseError) — event lifecycle rules when a TaskState is derived (start once, no progress before start, no progress after complete, complete once, 0–100%), and duplicate same-day events rejected when they are recorded.
  4. Engines (SchedulingError, BudgetingError) — nothing to schedule or budget, weighted budgets with no allocatable ancestor, and mandatory constraints the network cannot accommodate.

Testing

The suite uses Python's built-in unittest; there is no third-party test dependency. Currently 311 tests; all pass.

python -m unittest discover -s planscript/tests -t .
Test module Focus
test_parser.py Project/task/metadata/budget/dependency/constraint syntax, error messages, line references.
test_model.py TaskHierarchy behavior, budget validation, and constraint validation rules.
test_scheduler.py CPM examples across dependency types, branching, merging, float, critical paths, and soft and mandatory constraints.
test_tracking.py Event parsing, lifecycle/derivation rules, actual dates and costs.
test_budgeter.py Explicit, weighted, nested, rollup, remainder-cent, and unallocated cases.
test_performance.py Variance calculations against tracked plans.
test_reporter.py Status report figures, budget/progress invariants, data notices, and forecast fields.
test_forecaster.py Forecast durations and pins per tracking status, data-date edge cases, failure modes.
test_cli.py Subcommand behavior and exit codes through subprocesses.
test_scaling.py A generated 3,000-leaf plan: shape, long-chain critical path, tracking states and costs at scale, and a wall-clock ceiling for the status pipeline.
scale_bench.py Synthetic plan generator and per-stage timing benchmark (python -m planscript.tests.scale_bench); shared with test_scaling.py, not collected as tests.
test_projects.py Shared in-memory project fixtures for the scheduler tests.

Test conventions: fixtures live in test_projects.py; CLI tests call app.main in-process with one subprocess smoke run; tests assert on messages rather than tracebacks.

Current Gaps

The design intent and the implementation are not yet aligned in these areas. ROADMAP.md tracks them with priorities:

  • Calendars exist as a model but are unused, so schedules and actual durations ignore working days, holidays, and working hours.
  • _archive/ holds superseded code, and display.py retains unused menu functions.
  • The serializer is incomplete and not wired to the CLI, so plans can be read but not written back.
  • The status report lists every task but not the summary sections (overdue, blocked, late, upcoming deadlines/starts) that ROADMAP.md P1-3 still asks for.
  • Tracking design decisions that are not yet implemented: a decision on tracking summary tasks. (Same-day lifecycle precedence and duplicate same-day detection are enforced; future-dated events are settled: the data-date model excludes them and reports list them under Data Notices.)